Previous Work

Week of July 25, 2016

Work for weeks of 7/25/16, 8/1/16, 8/7/16, and 8/14/16 will include:

  • Reservoir: Crews continue to work on miscellaneous cleanup items on the exterior of the reservoir. Tennis court fencing and green screens are installed. Other railings and security fencing are expected to be done by 8/4/16. Final finishes on the ADA access ramp and rain gardens on the south side of the reservoir are expected to be done by 8/4/16. Railings and guardrail for the ADA ramp are expected to be complete by 8/9/16.
  • Pump Station: Operational testing of the pump station was completed by 7/22/16. Final cleanup work of the interior and exterior, including miscellaneous other items slated for correction, is expected to be complete by 8/1/16.
  • Landscaping / Site work: Site storm drain lines and waterline for the drinking fountain are expected to be complete by 8/1/16. Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading will be on-going the next couple weeks. Irrigation installation is on-going and expected to be complete by 8/12/16. Site landscaping which includes planting is expected to be done between 8/8/16 and 8/17/16. The picnic shelter is expected to be complete by 7/27/16, and the playground surfacing is expected to be complete by 8/3/16. Asphalt pathways in the park, including the parking lot and other pavement repairs, are expected to be done 8/18/16 and 8/19/16.
  • NOTE: The contractor anticipates working on site again the next 2 Saturdays in order to finish up with the site work in a timely manner. Saturday work hours are from 8:00 am to 4:30 pm.