Previous Work

Week of July 18, 2016

Work for weeks of 7/18/16, 7/25/16, and 8/1/16 will include:

  • Reservoir: Crews continue to work on miscellaneous cleanup items on the exterior of the reservoir. Tennis court fencing, green screens and other railings are expected to be done by 8/3/16. Final finishes on the ADA access ramp and rain gardens on the south side of the reservoir are expected to be done by 8/3/16.
  • Pump Station: Testing of the pump station has been on-going and is expected to be complete by 7/22/16. Final cleanup work of the interior and exterior, including miscellaneous other items slated for correction, is expected to be complete by 7/22/16 as well.
  • Pipeline & Utility Work: Utility work is nearly complete. Minor storm water drains are expected to be complete 7/25/16.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading will be on-going the next couple weeks. Irrigation installation is on-going. Site landscaping is expected to be done 8/3/16 to 8/12/16. Asphalt pathways in the park, the picnic shelter, and the playground surfacing are expected to be completed over the next 2-3 weeks.
  • NOTE: The contractor anticipates working on site the next 2 Saturdays in order to finish up with the site work in a timely manner. Saturday work hours are from 8:00 am to 4:30 pm.