Previous Work

Week of June 27, 2016

Work for weeks of 6/27/16, 7/4/16, and 7/11/16 will include:

  • Reservoir: Crews are no longer working on Saturday (6/25/16). The bulk of this work is expected to be complete by 7/5/16. The reservoir is currently being filled with water in anticipation of being online by 7/1/16. Crews will continue to work on miscellaneous items on the exterior of the reservoir including lights. Tennis court fencing, green screens and other railings are expected to be done by 7/8/16. Final finishes on the ADA access ramp and rain gardens on the south side of the reservoir are expected to be done by 7/14/16.
  • Pump Station: Crews are working to complete electrical work, HVAC, and minor mechanical work. Testing of the pump station is expected to begin the week of 7/4/16.
  • Pipeline & Utility Work: Utility work is nearly complete. The storm water piping and drainage swales are anticipated to be done by 7/1/16.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading has begun on the west side of the project moving east. Irrigation installation has begun, and tree and other vegetation planting will occur once irrigation installation is complete. Asphalt pathways in the park, the picnic shelter, and the playground surfacing are expected to be begin the week of 6/27/16. Completion of those items is expected the week of 7/4/16. Site fencing and sidewalks is anticipated to be complete the week of 7/11/16.
  • NOTE: The contractor expects to slurry seal the roadway impacted by the waterline trenching activities. Look for door hangers the week of 6/27/16 which will identify no parking zones for that work activity. This is for SW Ardenwood Street, SW Wilshire, and SW Melnore St. Also, no work will be performed on 7/4/16.