Previous Work

Week of June 13, 2016

Work for weeks of 6/13/16, 6/20/16, 6/27/16 and 7/4/16 will include:

  • Reservoir: Crews intend to work Saturdays (6/18/16, and 6/25/16) in order to complete the ADA access ramp on the south side of the reservoir. Work hours for Saturday work are 8am-4:30pm. The reservoir is expected to be filled with water the week of 6/20/16. Crews will continue to work on miscellaneous items on the exterior of the reservoir, and anticipate the reservoir to be fully functional by 6/29/16. Tennis court fencing, green screens and other railings are expected to be done by 7/8/16.
  • Pump Station: Crews are working to complete painting, electrical work and minor mechanical work. Plumbing work is complete. Electrical testing is expected to be done over the next few weeks, with Portland General Electric (PGE) expected to be on-site to connect building power on 6/23/16. The backup generator is installed and functional.
  • Pipeline & Utility Work: Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor site power conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site. Irrigation installation is expected to begin the week of 6/13/16. Asphalt pathways in the park, the picnic shelter, and the playground surfacing are expected to be done the week of 6/27/16.
  • NOTE: The contractor expects to slurry seal the roadway impacted by the waterline trenching activities. Look for door hangers the week of 6/27/16 which will identify no parking zones for that work activity.