Week of May 30, 2016

Work for weeks of 5/30/16, 6/6/16, 6/13/16 and 6/20/16 will include:

  • Reservoir: The final grading and gravel roadway around the reservoir is mostly complete as of 6/3/16. Crews intend to work Saturdays (6/4/16, 6/11/16, and 6/18/16) on the interior of the reservoir, the interior of the pump station, and potentially on the ADA access ramp on the south side of the reservoir. Work hours for Saturday work are 8am-4:30pm. Crews will continue to work on miscellaneous items on the interior of the reservoir, and anticipate the reservoir to be functional by 6/17/16. Tennis court fencing and other railings will be installed once the interior work is complete.
  • Pump Station: Crews are working to complete painting, mechanical, plumbing, and electrical work. Electrical testing is expected to be done over the next few weeks, with Portland General Electric (PGE) expected to be on-site to connect building power between 6/4/16 and 6/10/16. The backup generator is expected to be delivered and set in place on 6/9/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete. Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor utility conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site. Irrigation installation is expected to begin the week of 6/13/16.