Previous Work

Week of May 16, 2016

Work for weeks of 5/16/16, 5/23/16, 5/30/16 will include:

  • Reservoir: The final grading and gravel roadway around the reservoir is on-going and expected to be complete by 6/2/16. Crews may continue to work Saturday 5/21/16 on the interior of the reservoir. No major construction activities are anticipated. Crews will continue to work on miscellaneous items on the interior of the reservoir, and anticipate the reservoir to be functional by 6/9/16. Tennis court fencing and other railings will be installed once that is complete.
  • Pump Station: Crews are working to complete interior painting and other mechanical, plumbing, and electrical work. Exterior painting is anticipated to be complete by 5/31/16. Electrical testing is expected to be done over the next few weeks. Roofing and gutters is expected to be complete by 5/31/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete. Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor utility conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site.