Previous Work

Week of May 9, 2016

Work for weeks of 5/9/16, 5/16/16, and 5/23/16 will include:

  • Reservoir: As of 5/11/16, the majority of the backfill around the reservoir is complete. The final grading and gravel roadway will be completed following installation of site utilities. Crews intend to work Saturday 5/14/16 on the interior of the reservoir, and may also be working on the south side of the reservoir in order to accelerate the work for the reservoir access ramp.
  • Pump Station: Crews are installing roofing, and are working to complete interior painting and other mechanical, plumbing, and electrical work. Exterior painting is anticipated to be complete by 5/20/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete with the exception of final testing of the waterline which is currently underway. Utility work will continue on-site / within the park the next couple of weeks and includes construction of storm water piping, site power conduit, and other minor utility conduits. The sanitary sewer work is complete.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the access ramp and retaining walls leading up to the reservoir are expected to begin on 5/9/16. Tree and other vegetation planting will occur once irrigation is installed on-site.