Schedule Library
Meetings and Events

« Previous Work | Home | Previous Work »

Previous Work

Week of May 2, 2016

Work for weeks of 5/2/16, 5/9/16, and 5/16/16 will include:

  • Reservoir: The leak test on the reservoir is complete. The contractor is working to backfill around the reservoir. Crews intend to work Saturday 5/7/16 in order to backfill the reservoir in a timely manner. Backfill completion is expected by 5/16/16. Crews will continue to install reservoir access hatches and to correct minor flaws in the concrete.
  • Pump Station: Crews are installing roofing, and are working to complete interior painting and other mechanical, plumbing, and electrical work. Exterior painting is anticipated to begin 5/3/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete with the exception of final testing of the waterline. Waterline testing is currently underway. Utility work will continue on-site / within the park the next couple of weeks and includes construction of sanitary sewer piping, storm water piping, site power conduit, and other utility conduits. The bulk of this work is expected to be complete by 5/6/16 with only minor storm drain installation remaining on-site.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project. Installation of the access ramp and retaining walls leading up to the reservoir are expected to begin on 5/9/16. Crews have removed the majority of the invasive species within the vegetated corridor as required. Tree and other vegetation planting will occur once irrigation is installed on-site.