Previous Work

Week of April 25, 2016

Work for weeks of 4/25/16, 5/2/16 and 5/9/16 will include:

  • Reservoir: The contractor is continuing to test the reservoir for potential leaks, and inject any wall cracks that are seen to be visually leaking. The contractor has backfilled the south side of the reservoir, and is working to backfill the remaining areas around the reservoir. Crews intend to work Saturday 4/30/16 in order to backfill the reservoir in a timely manner. Crews will continue to install reservoir access hatches and to correct minor flaws in the concrete.
  • Pump Station: Crews are installing roofing, and are working to complete interior painting and other mechanical, plumbing, and electrical work. Exterior painting is anticipated to begin the week of 5/2/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete with the exception of final testing of the waterline. Utility work will continue on-site / within the park the next couple of weeks and includes construction of sanitary sewer piping, storm water piping, site power conduit, and other utility conduits. The final waterline connection to the pump station is expected to be complete the week of 4/25/16. The bulk of this work is expected to be complete by 5/6/16 with only minor site drains remaining.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project. Installation of the access ramp and retaining walls leading up to the reservoir are expected to begin following installation of the sewer line. Crews have removed the majority of the invasive species within the vegetated corridor as required. Tree and other vegetation planting will occur once irrigation is installed on-site.