Week of October 26, 2015

Week of 10/26/15: NOTE: Clean Water Services is currently performing work in the area near Ridgewood Elementary School unrelated to this project. For more information contact Gabe Sohler with Clean Water Services (sohlerg@cleanwaterservices.org). 

  • Reservoir: Concrete pours for walls and columns are nearing completion. The first two sections of roof slab have been poured.
  • Pump Station: Preparing for floor slab placement and other miscellaneous interior work for the pump station.
  • Pipeline: Pipeline work along SW Ardenwood St will be complete this week. Only connections and minor appurtenances along the route remain to be installed. Pipe work will now shift to the on-site work which will require deep trenches in order to place the pipe. This work is expected to take a few weeks to complete.
  • Landscaping: Work to construct the walking path on the north side of the forest area is on-going.
  • On 10/30/15 PGE will be replacing an old power pole on the site.

Week of 11/2/15:

  • Reservoir: Working to form and pour the reservoir roof, and complete the walls and columns.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.  
  • Pipeline: Pipeline work will continue on-site. The only remaining in-street pipe work will be to install minor appurtenances and complete testing and final connections.
  • Landscaping: Work to construct the walking path on the north side of the forest area is on-going.

Week of 11/9/15:

  • Reservoir: Working to form and pour the reservoir roof, and complete the remaining wall and columns.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.  
  • Pipeline: Pipeline work will continue on-site.
  • Landscaping: No landscape work anticipated this week.

Previous Work

Week of October 19, 2015

Week of 10/19/15:

  • Reservoir: Concrete pours for walls and columns are nearing completion. The first section of roof slab has been poured, and another one is scheduled this week.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.
  • Pipeline: Pipeline work is at the intersection of SW Ardenwood St and SW Burbank, and is advancing towards the reservoir site. The major in-street pipeline work is expected to be complete near the end of the week.
  • Landscaping: Work to construct the walking path on the north side of the forest area is on-going.

Week of 10/26/15:

  • Reservoir: Working to form and pour the reservoir roof, stairs, and complete the walls and columns.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.  
  • Pipeline: Pipeline work will continue on-site. The only remaining in-street pipe work will be to install minor appurtenances and complete testing and final connections.
  • Landscaping: Work to construct the walking path on the north side of the forest area is on-going.

Week of 11/2/15:

  • Reservoir: Working to form and pour the reservoir roof, and complete the remaining wall and columns.
  • Pump Station: Expect to pour the floor slab on the west side of the pump station.
  • Pipeline: Pipeline work will continue on-site.
  • Landscaping: No landscape work anticipated this week.

Pipeline Construction Update

Week of October 12, 2015

Beginning the week of October 12th open cut construction will take place at the intersection of 98th Avenue and Ardenwood Street. The work is expected to take all week. The intersection will be open during the daytime work hours (7 am-6 pm) but have flaggers present to direct and possibly stop traffic when necessary.

Metal plates/sheeting will be put down at night enabling cars to drive through the area during non-work hours. Construction at the intersection is expected to be finished by October 16th and continue moving east on Ardenwood Street toward the reservoir site.

Please obey flaggers and all construction signs. We appreciate your continued patience during construction.


Previous Work

Week of October 5, 2015

Week of 10/5/15:

  • Reservoir: Concrete pours for walls and columns are nearing completion. Working to form the reservoir roof.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.
  • Pipeline: Pipeline work is at the eastern end of SW Ardenwood St moving towards the reservoir site.
  • Landscaping: Work to construct the walking path on the south side of the site is expected to be on-going when crews are available.

Week of 10/12/15:

  • Reservoir: Working to form the reservoir roof. Expect to pour the first roof slab on 10/13/15.
  • Pump Station: Preparing for floor slab placement and other miscellaneous work for the pump station.  
  • Pipeline: Pipeline work continues along SW Ardenwood St heading towards the reservoir site. Expect traffic delays as the pipeline approaches the site.
  • Landscaping: Work to construct the walking path on the south side of the site is expected to be on-going when crews are available.

Week of 10/19/15:

  • Reservoir: Pour portion of northern roof slab. Prepare for additional concrete pours including completing the remaining walls.
  • Pump Station: Masonry installation scheduled to begin.
  • Pipeline: Pipeline work will be approaching the reservoir site. Expect traffic delays on SW Ardenwood St.
  • Landscaping: Work to construct the walking path on the south side of the site is expected to be on-going when crews are available.