New pedestrian bridge

Week of January 25, 2016

Work for weeks of 1/25/16, 2/1/16 and 2/8/16 will include:

  • Reservoir: All major concrete pours are complete. Contractor will be removing interior shoring, working on interior piping, installing reservoir hatches and appurtenances, and correcting minor flaws in the concrete. Reservoir leakage testing will then follow.
  • Pump Station: Masonry work continues and is expected to be complete by 1/29/16. Other mechanical, plumbing, and electrical work inside the pump station will be on-going. Roofing work has begun and will continue over the next couple of weeks.
  • Pipeline & Utility Work: Off-site work to install pipeline appurtenances is nearly complete. Contractor is working to pressure test the new water pipe. Work has begun on the sanitary sewer line on Ardenwood St. Sanitary sewer and other on-site storm water piping and water line pipe installation will continue the next couple of weeks.
  • Landscaping: The pedestrian trail bridge is complete (see photo above). Surface rock for the loop trail is nearly complete.

Previous Work

Week of January 4, 2016

NOTE: No work on-site is planned on 1/18/16 (Martin Luther King Jr. Day)

Work for weeks of 1/4/16, 1/11/16 and 1/18/16 will include:

  • Reservoir: The last major roof concrete pour is being done 1/8/16. There will be one more smaller pour on 1/15/16 (weather dependent). Once all the pours are complete, work will be done to install interior piping and to correct minor flaws in the concrete. Reservoir leakage testing will then follow.
  • Pump Station: Masonry work continues and is expected to be complete by 1/11/16. Other mechanical, plumbing, and electrical work inside the pump station is on-going. Roofing will begin to be installed once the masonry work is complete.
  • Pipeline: Pipeline work on-site continues. The contractor is working to install various appurtenances along the pipeline route, make final connections, and pressure test the newly installed pipe. Crews will be completing work at Wilshire St, and at the corner of Scenic Dr. and SW Melnore St. There will also be on-going pipe and utility installation on-site in the coming weeks as the reservoir is completed.
  • Landscaping: The pedestrian trail bridge installation began this week. Surface rock for path is expected to be placed the starting 1/11/16.

Previous Work

Week of December 14, 2014

NOTE: No work on-site is planned for the following dates: 12/24/2015-12/25/2015, and 1/1/2016.

Work for weeks of 12/14/15, 12/21/15 and 12/28/15 will include:

  • Reservoir: Roof pour being done 12/15/15. There are 3 large roof pours remaining (roughly 1 per week) which are scheduled for completion by 1/4/2016 (weather dependent).
  • Pump Station: Masonry work is expected to be complete by the end of December. Other mechanical and electrical work inside the pump station will be on-going. Roofing will begin to be installed the first week of January.
  • Pipeline: Pipeline work on-site continues. The contractor completed grouting of the interior joints of the pipe, and will be working to install various appurtenances along the pipeline route. Crews will be completing work at the connection points on Wilshire St, and SW Melnore St.
  • Landscaping: Bridge for trail is being delivered 12/15/15 and will be installed once on-site. Surface rock for path is expected to be placed the first week on January.

Previous Work

Week of November 30, 2015

Week of 11/30/15:

  • Reservoir: Concrete pours for walls and columns are complete. The remaining roof pours are scheduled for completion by the end of December.
  • Pump Station: Masonry work and other mechanical work will be on-going.
  • Pipeline: Pipeline work is nearing completion on-site. The contractor will begin grouting the interior joints of the pipe, and installing various appurtenances. Crews will be digging at the connection points on Wilshire St, and SW Melnore St.
  • Landscaping: Base rock for the walking path including steps is complete. A final layer of rock will be placed once the bridge is set in place.

Week of 12/7/15 and 12/14/15:

  • Reservoir: Working to complete the concrete roof.
  • Pump Station: Working on masonry walls and other miscellaneous items.
  • Pipeline: Pipeline work will continue on-site. In-street pipe work to install minor appurtenances and complete testing and final connections will be nearing completion.
  • Landscaping: Anticipate installation of pedestrian bridge. Work to follow to finalize trail grading.