Week of June 27, 2016

Work for weeks of 6/27/16, 7/4/16, and 7/11/16 will include:

  • Reservoir: Crews are no longer working on Saturday (6/25/16). The bulk of this work is expected to be complete by 7/5/16. The reservoir is currently being filled with water in anticipation of being online by 7/1/16. Crews will continue to work on miscellaneous items on the exterior of the reservoir including lights. Tennis court fencing, green screens and other railings are expected to be done by 7/8/16. Final finishes on the ADA access ramp and rain gardens on the south side of the reservoir are expected to be done by 7/14/16.
  • Pump Station: Crews are working to complete electrical work, HVAC, and minor mechanical work. Testing of the pump station is expected to begin the week of 7/4/16.
  • Pipeline & Utility Work: Utility work is nearly complete. The storm water piping and drainage swales are anticipated to be done by 7/1/16.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading has begun on the west side of the project moving east. Irrigation installation has begun, and tree and other vegetation planting will occur once irrigation installation is complete. Asphalt pathways in the park, the picnic shelter, and the playground surfacing are expected to be begin the week of 6/27/16. Completion of those items is expected the week of 7/4/16. Site fencing and sidewalks is anticipated to be complete the week of 7/11/16.
  • NOTE: The contractor expects to slurry seal the roadway impacted by the waterline trenching activities. Look for door hangers the week of 6/27/16 which will identify no parking zones for that work activity. This is for SW Ardenwood Street, SW Wilshire, and SW Melnore St. Also, no work will be performed on 7/4/16.

Previous Work

Week of June 13, 2016

Work for weeks of 6/13/16, 6/20/16, 6/27/16 and 7/4/16 will include:

  • Reservoir: Crews intend to work Saturdays (6/18/16, and 6/25/16) in order to complete the ADA access ramp on the south side of the reservoir. Work hours for Saturday work are 8am-4:30pm. The reservoir is expected to be filled with water the week of 6/20/16. Crews will continue to work on miscellaneous items on the exterior of the reservoir, and anticipate the reservoir to be fully functional by 6/29/16. Tennis court fencing, green screens and other railings are expected to be done by 7/8/16.
  • Pump Station: Crews are working to complete painting, electrical work and minor mechanical work. Plumbing work is complete. Electrical testing is expected to be done over the next few weeks, with Portland General Electric (PGE) expected to be on-site to connect building power on 6/23/16. The backup generator is installed and functional.
  • Pipeline & Utility Work: Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor site power conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs, sidewalks, and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site. Irrigation installation is expected to begin the week of 6/13/16. Asphalt pathways in the park, the picnic shelter, and the playground surfacing are expected to be done the week of 6/27/16.
  • NOTE: The contractor expects to slurry seal the roadway impacted by the waterline trenching activities. Look for door hangers the week of 6/27/16 which will identify no parking zones for that work activity.

Previous Work

Week of May 30, 2016

Work for weeks of 5/30/16, 6/6/16, 6/13/16 and 6/20/16 will include:

  • Reservoir: The final grading and gravel roadway around the reservoir is mostly complete as of 6/3/16. Crews intend to work Saturdays (6/4/16, 6/11/16, and 6/18/16) on the interior of the reservoir, the interior of the pump station, and potentially on the ADA access ramp on the south side of the reservoir. Work hours for Saturday work are 8am-4:30pm. Crews will continue to work on miscellaneous items on the interior of the reservoir, and anticipate the reservoir to be functional by 6/17/16. Tennis court fencing and other railings will be installed once the interior work is complete.
  • Pump Station: Crews are working to complete painting, mechanical, plumbing, and electrical work. Electrical testing is expected to be done over the next few weeks, with Portland General Electric (PGE) expected to be on-site to connect building power between 6/4/16 and 6/10/16. The backup generator is expected to be delivered and set in place on 6/9/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete. Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor utility conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site. Irrigation installation is expected to begin the week of 6/13/16.

Previous Work

Week of May 16, 2016

Work for weeks of 5/16/16, 5/23/16, 5/30/16 will include:

  • Reservoir: The final grading and gravel roadway around the reservoir is on-going and expected to be complete by 6/2/16. Crews may continue to work Saturday 5/21/16 on the interior of the reservoir. No major construction activities are anticipated. Crews will continue to work on miscellaneous items on the interior of the reservoir, and anticipate the reservoir to be functional by 6/9/16. Tennis court fencing and other railings will be installed once that is complete.
  • Pump Station: Crews are working to complete interior painting and other mechanical, plumbing, and electrical work. Exterior painting is anticipated to be complete by 5/31/16. Electrical testing is expected to be done over the next few weeks. Roofing and gutters is expected to be complete by 5/31/16.
  • Pipeline & Utility Work: The in-street / off-site pipe work is complete. Utility work will continue on-site / within the park and includes construction of storm water piping, and other minor utility conduits.
  • Landscaping / Site work: Crews are working to place miscellaneous concrete curbs and other features on the site. Site grading has begun on the west side of the project moving east. Installation of the retaining walls, ADA access ramp, and stairs leading up to the reservoir roof is underway, and will continue for several weeks. Tree and other vegetation planting will occur once irrigation is installed on-site.