Week of December 8, 2014

Week of 12/08: Tank demolition, excavation and soil nail shoring will continue.

Week of 12/15: Tank demolition, excavation and soil nail shoring will continue. 

Week of 12/22: Crushing concrete from demolished reservoir, soil nail wall installation, and excavation for pump station foundation. No work will be done on Christmas Day.


Previous Work

Soil nail wall

Soil nail wall

December 3, 2014

Week of 12/01: Tank demolition, excavation and soil nail shoring (see photo) will continue.

Week of 12/08: Tank demolition, excavation and soil nail shoring will continue. 

Week of 12/15: Crushing concrete from demolished reservoir, soil nail wall installation, and excavation for pump station foundation.


 


Previous Work

Tank demolition

November 17, 2014

Week of 11/17: Tank demolition and excavation will continue (see photos below). Contractor will begin soil nail shoring installation.

Week of 11/24: Tank demolition, excavation and soil nail installation will continue. No work expected 11/27 or 11/28

Week of 12/1: Crushing concrete from demolished reservoir, soil nail wall installation, and excavation for pump station foundation.


Previous Work

November 12, 2014

Week of 11/10: Tank demolition began Monday

Week of 11/17: Tank demolition and excavation will continue

Week of 11/24: Tank demolition and excavation will continue.