Schedule Library
Meetings and Events

Archives

Previous Work

Week of January 26, 2015

Week of 1/26/15: Excavation including rock removal, and soil nail shoring will continue.

Week of 2/2/15: Excavation including rock removal, and soil nail shoring will continue. Blasting in order to remove rock for the pump station foundation is anticipated starting Thursday 2/5/2015.The contractor has installed several safety measures to ensure the job-site safety as well as neighborhood safety. This includes installation of vibration sensors at various locations to ensure no nearby structures are damaged during blasting,

Read More

Previous Work

Week of January 12, 2015

Week of 1/12/15: Existing reservoir walls are demolished, and the existing base slab is being removed. Excavation including rock removal continues.

Week of 1/19/15: Excavation including rock removal, demolition of the existing base slab, and soil nail shoring will continue.No work will be done on 1/19/15 due to the holiday.

Week of 1/26/15: Excavation including rock removal, and soil nail shoring will continue. Expect to start forming the pump station foundation.

Week of 2/2/15: Excavation including rock removal to continue. Soil nail shoring is expected to be complete this week. Forming pump station foundation in preparation for concrete.


Previous Work

Week of December 29, 2014

Week of 12/29: Tank demolition, excavation including rock removal, and soil nail shoring will continue. No work will be done on 1/1/15, however, the contractor intends to work on 1/2/15.

Week of 1/5: Tank demolition, excavation, crushing concrete from the demolished reservoir, and soil nail shoring will continue.

Week of 1/12: Tank demolition, excavation, crushing concrete from the demolished reservoir, and soil nail shoring will continue. 


Previous Work

Excavation continues

Week of December 15, 2014

Week of 12/15: Tank demolition, excavation including rock removal, and soil nail shoring will continue.

Week of 12/22: Tank demolition, excavation including rock removal, and soil nail shoring will continue. No work expected 12/25/14 or 12/26/14.

Week of 12/29: Crushing concrete from demolished reservoir, soil nail wall installation, and excavation for pump station foundation. No work will be done 1/1/15.