Week of March 9, 2015

Week of 3/9/15NOTE: TREE REMOVAL SCHEDULE HAS BEEN ADVANCED FROM PREVIOUS SCHEDULE. The contractor will work to clear trees between the project site and Ridgewood Elementary School in preparation of upcoming waterline work. The contractor is placing and compacting rock in preparation of pouring concrete. Working to install pipe beneath the reservoir.

Week of 3/16/15: Continuing to prepare to pour concrete for the pump station and reservoir foundations. Includes pouring concrete for foundation support and constructing concrete forms. Pipeline work in front of Ridgewood Elementary will start the end of this week (3/21/15).

Week of 3/23/15: Pouring concrete for the pump station foundation and preparing for concrete for the reservoir foundation. Pipeline work in front of Ridgewood Elementary will continue through the end of this week.

Upcoming events: Waterline work in front of Ridgewood Elementary School expected during spring break 3/21-3/29. Access through the school parking lot will be closed during that time. Additional pipeline activities are anticipated in April on Melnore St and Wilshire St.


Previous Work

Week of March 2, 2015

Week of 3/2/15: Soil nail shoring is complete. The contractor is working to prepare the subgrade for pouring concrete. This includes placing and compacting rock and final grading work. Also preparing to install pipe beneath the reservoir.

Week of 3/9/15: Continuing to prepare to pour concrete for the pump station and reservoir foundations. Includes pouring concrete for foundation supports and constructing concrete forms.

Week of 3/16/15: Pouring concrete for the pump station foundation and preparing for concrete for the reservoir foundation. Pipeline work in front of Ridgewood Elementary will start the end of this week (3/21/15).

Upcoming events: Waterline work in front of Ridgewood Elementary School expected during spring break 3/21-3/29. Access through the school parking lot will be closed during that time. Tree removal along the pipeline route to the south of the project (between Ridgewood Elementary and the project site) is expected to occur in April. Additional pipeline activities are anticipated in April on Melnore St and Wilshire St.


Previous Work

Week of February 16, 2015

Week of 2/16/15: Blasting was successfully completed for this portion of the project. All vibration levels were kept within the set limits. Excavation including rock removal, and soil nail shoring continues.

Week of 2/23/15: Excavation including rock removal for this portion of the project is nearly complete. Soil nail shoring is expected to be complete. Preparing to pour concrete for the pump station foundation and reservoir foundation. 

Week of 3/2/15: Pouring concrete for the pump station foundation and preparing for concrete for the reservoir foundation. Piping under the reservoir foundation will be installed.

Week of 3/9/15: Concrete foundation activities will continue.

Upcoming events: Waterline work in front of Ridgewood Elementary School expected during spring break 3/21-3/29. Access through the school parking lot will be closed during that time. Tree removal along the pipeline route to the south of the project (between Ridgewood Elementary and the project site) is expected to occur in April. Additional pipeline activities are anticipated in April on Melnore St and Wilshire St.


Previous Work

February 6, 2015

Week of 2/2/15: Excavation including rock removal, and soil nail shoring will continue. Demolition of the existing reservoir is complete and the demolition crew is demobilizing their equipment on 2/6/15. Blasting in order to remove rock for the pump station foundation is anticipated starting Friday 2/6/2015. The contractor has installed several safety measures to ensure the job-site safety as well as neighborhood safety. This includes installation of vibration sensors at various locations to ensure no nearby structures are damaged during blasting. Contractor is expecting to work Saturday 2/7/2015 on the on-site soil nail wall installation. No other work is anticipated that day.

Week of 2/9/15: Excavation including rock removal, and soil nail shoring will continue. Blasting is expected intermittently in order to remove rock for the pump station foundation. Preparing to pour concrete for the pump station foundation. 

Week of 2/16/15: Excavation including rock removal, and soil nail shoring is expected to be nearing completion for this portion of the project. Preparing to pour concrete for the pump station foundation.

Week of 2/2315: Preparing to pour concrete for the pump station foundation. Preparing reservoir subgrade in order to begin forming the concrete base slab.