Pump station

Week of 4/6/15: The first concrete pour for the pump station occurred on 4/2/15 (see picture to the right). The contractor will be placing and compacting rock in preparation of pouring concrete for the reservoir foundation. Will continue to install concrete forms and rebar for concrete foundations. Concrete pours will be occurring frequently (~once/week). Pipeline work is being done on Wilshire St, east of Knollcrest Dr.

Week of 4/13/15:  Pipeline work will continue on Wilshire St, east of Knollcrest Dr. Contractor will be forming and pouring concrete on-site.

Week of 4/20/15: Pipeline work will shift to the intersection of Scenic Dr, and SW Melnore St. Pipeline work will then continue on SW Melnore St west towards Ridgewood Elementary School. Work directly in front of the school will not begin again until after June 15th. Forming and pouring concrete will continue on-site. Night time work is expected on Hwy 217 this week for some miscellaneous pipeline work.

Week of 4/27/15: Pipeline work is expected to continue on SW Melnore St. Contractor will be forming and pouring concrete on-site.


Previous Work

Week of March 30, 2015

Week of 3/30/15: The contractor will be placing and compacting rock in preparation of pouring concrete for the reservoir foundation. Will begin to install concrete forms and rebar for concrete foundations. The first official structural concrete pour is scheduled for 4/2/15 to pour part of the foundation for the pump station.

Week of 4/6/15:  Pipeline work will begin on Wilshire St, east of Knollcrest Dr. Contractor will be forming and pouring concrete. Concrete pours will occur almost weekly from this point.

Week of 4/13/15: Pipeline work will continue on Wilshire St, east of Knollcrest Dr. Forming and pouring concrete will continue on-site.

Week of 4/20/15: Pipeline work will shift to a tie-in connection at the intersection of Scenic Dr, and SW Melnore St. Pipeline work will then continue on SW Melnore St west towards Ridgewood Elementary School. Work in front of the school will not begin again until summer break. Forming and pouring concrete will continue on-site.


Previous Work

Week of March 23, 2015

Week of 3/23/15: The contractor will be placing and compacting rock in preparation of pouring concrete. Will begin to install concrete forms and rebar for concrete foundations. Pipeline work in front of Ridgewood Elementary will occur this week including some pipeline relocation work at Scenic Dr. Access through the school parking lot will be closed this week. Additional work in front of the school will be done during the summer months.

Week of 3/30/15:  Forming and pouring concrete. Installing below slab electrical conduit and drain piping.

Read More

Previous Work

Week of March 16, 2015

Upcoming events: Contractor is anticipating pouring concrete on Saturday 3/14/15. Waterline work in front of Ridgewood Elementary School is expected during spring break 3/21-3/29. Access through the school parking lot will be closed during that time. Additional pipeline activities are anticipated in April on Melnore St and Wilshire St.

Week of 3/16/15: The contractor will be placing and compacting rock in preparation of pouring concrete. Will begin to install concrete forms and rebar for concrete foundations. Pipeline work in front of Ridgewood Elementary will start the end of this week (3/21/15). A large crane will be delivered to the site and assembled on 3/19/15.

Week of 3/23/15:  Pipeline work in front of Ridgewood Elementary will continue through the end of this week. Installing forms and rebar in preparation of concrete.

Week of 3/30/15: Forming and pouring concrete.